CAUTION / NOTICE / HINT
Tech Tips
Use the same procedure for RHD and LHD vehicles.
The procedure listed below is for LHD vehicles.
PROCEDURE
INSTALL COMBINATION METER ASSEMBLY
Connect the connectors.
Install the combination meter assembly with the 4 screws.
INSTALL NO. 2 INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY
Connect the connectors.
Attach the 9 claws to install the No. 2 instrument cluster finish panel sub-assembly.
Attach the 4 claws.
INSTALL NO. 2 INSTRUMENT CLUSTER FINISH PANEL GARNISH
INSTALL NO. 1 INSTRUMENT CLUSTER FINISH PANEL GARNISH
INSTALL LOWER INSTRUMENT PANEL PAD SUB-ASSEMBLY LH
INSTALL NO. 2 INSTRUMENT PANEL FINISH PANEL CUSHION
ENABLE AUTOAWAY/RETURN FUNCTION (for Power Tilt and Power Telescopic Steering Column)
Restore the autoaway/return function setting to the previous condition by changing the customize parameter Click here.