VANE PUMP(for 1UR-FE) INSTALLATION

PROCEDURE


  1. INSTALL VANE PUMP ASSEMBLY


    1. Install the vane pump with the 2 bolts.

      Torque:
      21 N*m  { 214 kgf*cm, 15 ft.*lbf }
  2. CONNECT SUCTION HOSE


    1. Connect the suction hose to the vane pump assembly with the clip.

  3. CONNECT PRESSURE FEED TUBE


    1. Install a new gasket to the pressure feed tube.

    2. Connect the pressure feed tube with the union bolt.

      Torque:
      50 N*m  { 510 kgf*cm, 37 ft.*lbf }
  4. CONNECT POWER STEERING OIL PRESSURE SENSOR CONNECTOR


    1. Connect the connector.

    2. Attach the wire harness clamp.

  5. INSTALL FAN AND GENERATOR V BELT

    Click here

  6. INSTALL AIR CLEANER AND HOSE

    Click here

  7. INSTALL V-BANK COVER SUB-ASSEMBLY

    Click here

  8. INSTALL FRONT FENDER APRON TRIM PACKING A

    Click here

  9. INSTALL FRONT WHEEL RH

    Click here

  10. ADD POWER STEERING FLUID

  11. BLEED POWER STEERING FLUID

    Click here

  12. INSPECT FOR POWER STEERING FLUID LEAK

  13. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

    Note

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected Click here.