SHIFT LEVER(w/o Entry and Start System) INSTALLATION

PROCEDURE


  1. INSTALL TRANSMISSION FLOOR SHIFT ASSEMBLY

    B001YFLE02

    1. Install the floor shift with the 4 bolts. Tighten the bolts in the order shown in the illustration.

      Torque:
      14 N*m  { 143 kgf*cm, 10 ft.*lbf }
    2. Connect the 2 connectors.

  2. CONNECT FLOOR SHIFT GEAR SHIFTING ROD SUB-ASSEMBLY

    B001XL7E01

    1. Turn the control shaft lever RH of the park/neutral position switch counterclockwise until it stops, and then turn it clockwise 2 notches to set it to the N position.

    2. Move the shift lever to N.

    3. B001XSQE01
      *1 Lever

      Temporarily install the floor shift gear shifting rod with the nut.

    4. Tighten the nut while lightly pushing the lever rearward.

      Torque:
      13 N*m  { 130 kgf*cm, 9 ft.*lbf }
  3. INSTALL FRONT CONSOLE BOX