MOTOR CABLE INSTALLATION

PROCEDURE


  1. INSTALL MOTOR CABLE

    Note

    Wear insulated gloves.


    1. Install the motor cable to the hybrid transaxle assembly with the 3 bolts.

      Torque:
      10 N*m  { 102 kgf*cm, 7 ft.*lbf }

      Note

      Keep the sealing surface of the motor cable and the connector terminal joint free of foreign matter.

    2. Engage the 2 claws to install a new terminal cap.

      Note

      When installing the terminal cap to the motor cable terminal block, keep the sealing surface free of foreign matter.

    3. B001N36

      Place the motor cable connector shell in position and install it with the 2 bolts.

      Torque:
      10 N*m  { 102 kgf*cm, 7 ft.*lbf }
    4. Connect the 3 clamps.

  2. INSTALL INVERTER TRAY BRACKET (for 2ZR-FXE)

    Click here

  3. INSTALL INVERTER TRAY BRACKET (for 5ZR-FXE)

    Click here

  4. INSTALL INVERTER RESERVE TANK ASSEMBLY (for 2ZR-FXE)

    Click here

  5. INSTALL INVERTER RESERVE TANK ASSEMBLY (for 5ZR-FXE)

    Click here

  6. INSTALL INVERTER WITH CONVERTER ASSEMBLY

    Click here

  7. CONNECT WATER HOSE

    Click here

  8. CONNECT NO. 2 ENGINE ROOM WIRE

    Click here

  9. REMOVE INVERTER COVER

    Click here

  10. CONNECT NO. 2 ENGINE WIRE

    Click here

  11. CONNECT MOTOR CABLE

    Click here

  12. CONNECT GENERATOR CABLE

    Click here

  13. CONNECT FRAME WIRE

    Click here

  14. CHECK HIGH VOLTAGE CABLE CONNECTION

    Click here

  15. INSTALL INVERTER COVER

    Click here

  16. INSTALL ENGINE ROOM MAIN WIRE

    Click here

  17. INSTALL NO. 1 INVERTER BRACKET

    Click here

  18. INSTALL SERVICE PLUG GRIP

    Click here

  19. CONNECT CABLE TO NEGATIVE AUXILIARY BATTERY TERMINAL

    Note

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected Click here.

  20. INSTALL REAR FLOOR BOARD UPPER NO. 3 PLATE

    Click here

  21. INSTALL DECK FLOOR BOX RH

    Click here

  22. INSTALL REAR NO. 3 FLOOR BOARD

    Click here

  23. INSTALL REAR DECK FLOOR BOX

    Click here

  24. INSTALL REAR NO. 2 FLOOR BOARD

    Click here

  25. ADD COOLANT (for Inverter)

    Click here

  26. INSPECT FOR COOLANT LEAK (for Inverter)

    Click here

  27. INSTALL RADIATOR SUPPORT OPENING COVER

    Click here

  28. INSTALL INVERTER COVER ASSEMBLY LH (w/ Cover)

    Click here

  29. INSTALL NO. 1 ENGINE UNDER COVER (for 2ZR-FXE)

    Click here

  30. INSTALL NO. 1 ENGINE UNDER COVER (for 5ZR-FXE)

    Click here

  31. INSTALL FRONT LOWER BUMPER ABSORBER (for 2ZR-FXE)

    Click here

  32. INSTALL FRONT LOWER BUMPER ABSORBER (for 5ZR-FXE)

    Click here