ROOF DRIP SIDE FINISH MOULDING INSTALLATION


  1. INSTALL NO. 1 ROOF DRIP SIDE FINISH MOULDING CLIP

    Note

    When installing new clips, remove the double-sided tape remaining where the clips will be installed on the body and clean the body with a non-residue solvent.


    1. A01HVQAE01
      Text in Illustration
      *1 Adhesive
      *a 2 to 3 mm Bead of Adhesive

      Apply a 2 to 3 mm (0.0787 to 0.118 in.) bead of adhesive (3M DP-105 or equivalent) to new No. 1 roof drip side finish moulding clips.

      Tech Tips

      Adhesive strength (tensile strength): 13.7 MPa (140.0 kgf/cm2, 1987 psi) or more (when the temperature is 23°C (73°F))

    2. Press and install the 2 No. 1 roof drip side finish moulding clips.

    3. Install the clips to the positions on the roof panel shown in the illustration. Determine the locations and firmly press and install the 2 No. 1 roof drip side finish moulding clips after lightly applying adhesive (3M DP-105 or equivalent).

      A01HU34E01
      Text in Illustration
      *A for Front *B for Rear
      *1 Protruding Part - -
      Standard Dimension
      Installation Area Dimension Measurement
      for Front A 4.0 mm (0.157 in.)
      B 4.0 mm (0.157 in.)
      C 1.8 mm (0.0709 in.)
      D 1.8 mm (0.0709 in.)
      for Rear E 4.0 mm (0.157 in.)
      F 4.0 mm (0.157 in.)
      G 1.8 mm (0.0709 in.)
      H 1.8 mm (0.0709 in.)
    4. Install the roof drip center side finish moulding when 20 minutes or more have elapsed after pressing and installing 2 new No. 1 roof drip side finish moulding clips.

      Tech Tips


      • Initial hardening time: 20 minutes

      • Complete hardening time: 48 hours

  2. INSTALL CENTER ROOF DRIP SIDE FINISH MOULDING


    1. A01HTRN

      Engage the 2 clips and install the center roof drip side finish moulding.