INSTALL ROOF DRIP SIDE FINISH MOULDING CLIP
Note
If reusing the clips, do not remove the double-sided tape remaining on the clips and where the clips will be installed on the body.
If installing new clips, remove the double-sided tape remaining where the clips will be installed on the body and clean the body with a non-residue solvent.
Apply a 2 to 3 mm (0.0787 to 0.118 in.) bead of adhesive (3M DP-105 or equivalent) to new roof drip side finish moulding clips.
Tech Tips
Adhesive strength (tensile strength): 13.7 MPa (140 kgf/cm2) or more (when the temperature is 23°C (73°F).)
Press and install the 2 roof drip side finish moulding clips.
Install the clips to the positions on the roof panel shown in the illustration. Determine the locations and firmly press and install the 2 roof drip side finish moulding clips after lightly applying adhesive (3M DP-105 or equivalent).
| Item | Dimension |
|---|---|
| A | 4.9 mm (0.193 in.) |
| B | 8.4 mm (0.331 in.) |
| C | 2.1 mm (0.0827 in.) |
| D | 3.0 mm (0.118 in.) |
| E | 3.0 mm (0.118 in.) |
| F | 5.6 mm (0.221 in.) |
| G | 10.4 mm (0.409 in.) |
Install the roof drip center side finish moulding when 20 minutes or more have elapsed after pressing and installing the 2 roof drip side finish moulding clips.
Tech Tips
Initial hardening time: 20 minutes
Complete hardening time: 48 hours
INSTALL ROOF DRIP CENTER SIDE FINISH MOULDING
Engage the 2 clips and install the roof drip center side finish moulding as shown in the illustration.