INSPECT CHARCOAL CANISTER ASSEMBLY
Visually check the charcoal canister assembly.
Visually check the charcoal canister assembly for cracks or damage.
If cracks or damage are found, replace the charcoal canister assembly.
Check canister operation.
| *a | Vent Line Port |
| *b | Air Line Port |
| *c | Purge Line Port |
| *d | Air |
With the purge line port closed, blow 0.5 kPa (0.005 kgf/cm2, 0.1 psi) of air into the vent line port, and check that air flows from the air line port.
If the result is not as specified, replace the charcoal canister assembly.
| *a | Vent Line Port |
| *b | Air Line Port |
| *c | Purge Line Port |
| *d | Air |
With the vent line port closed, blow 0.5 kPa (0.005 kgf/cm2, 0.1 psi) of air into the air line port, and check that air flows from the purge line port.
If the result is not as specified, replace the charcoal canister assembly.
Check for air leaks.
| *1 | Pressure Gauge |
| *a | Vent Line Port |
| *b | Air Line Port |
| *c | Purge Line Port |
Connect a pressure gauge to the vent line port of the charcoal canister assembly.
With the purge line port and the air line port closed, apply 20 kPa (150 mmHg, 5.91 in.Hg) of pressurized air into the vent line port, then confirm that pressure is retained for 1 minute.
If the result is not as specified, replace the charcoal canister assembly.