DESCRIPTION
Refer to "SRS Warning Light Remains ON" Click here.
WIRING DIAGRAM
Refer to "SRS Warning Light Remains ON" Click here.
INSPECTION PROCEDURE
PROCEDURE
CHECK AUXILIARY BATTERY
Turn the power switch OFF.
Measure the voltage of the auxiliary battery.
| Standard voltage |
|---|
| 11 to 14 V |
| NG |
|
REPLACE OR RECHARGE AUXILIARY BATTERY |
| OK |
|
CHECK CONNECTOR
Turn the power switch OFF.
Disconnect the negative (-) terminal cable from the auxiliary battery, and wait for at least 90 seconds.
Check that the connector is properly connected to the No. 1 meter ECU sub-assembly.
| OK |
|---|
| The connector is properly connected. |
| NG |
|
CONNECT CONNECTOR PROPERLY |
| OK |
|
CHECK HARNESS AND CONNECTOR (SOURCE VOLTAGE OF NO. 1 METER ECU SUB-ASSEMBLY - AUXILIARY BATTERY AND BODY GROUND)
Turn the power switch OFF.
Disconnect the negative (-) terminal cable from the auxiliary battery, and wait for at least 90 seconds.
Disconnect the L124 connector from the No. 1 meter ECU sub-assembly.
Connect the negative (-) terminal cable to the auxiliary battery, and wait for at least 2 seconds.
Turn the power switch ON (IG).
Measure the voltage according to the value(s) in the table below.
| Standard voltage | ||||||
|---|---|---|---|---|---|---|
|
Turn the power switch OFF.
Measure the resistance according to the value(s) in the table below.
| Standard resistance | ||||||
|---|---|---|---|---|---|---|
|
| NG |
|
REPAIR OR REPLACE HARNESS OR CONNECTOR |
| OK |
|
CHECK SRS WARNING LIGHT
Turn the power switch OFF.
Disconnect the negative (-) terminal cable from the auxiliary battery, and wait for at least 90 seconds.
Connect the connector to the No. 1 meter ECU sub-assembly.
Connect the negative (-) terminal cable to the auxiliary battery, and wait for at least 2 seconds.
Turn the power switch ON (IG).
Check the SRS warning light condition.
Note
Make sure that nobody is in the vehicle.
| OK |
|---|
| After the primary check period, the SRS warning light goes off for approximately 10 seconds and then remains on. |
Tech Tips
The primary check period is approximately 6 seconds after the power switch is turned ON (IG).
| NG |
|
GO TO METER / GAUGE SYSTEM Click here |
| OK |
|
REPLACE CENTER AIRBAG SENSOR ASSEMBLY Click here