REMOVE FUEL PUMP ASSEMBLY (for Bank 1)
REMOVE FUEL PUMP ASSEMBLY (for Bank 2)
DISCONNECT WIRE HARNESS
Remove the 3 connectors and connector clamp.
Using a screwdriver, detach the claw and disconnect the No. 4 connector holder.
Disconnect the 5 connectors and grommet from the engine room ECU box.
Disconnect the 8 connectors and 3clamps.
Disconnect the 5 connectors and 7clamps.
Remove the 2 bolts and disconnect the 2 ground wires.
Remove the No. 1 engine room relay block cover (for RHD).
Remove the nut (for RHD).
Disconnect the clamp, detach the 2 claws and disconnect the wire harness from the engine room No. 1 relay block (for RHD).
Remove the bolt, and disconnect the ground cable.
Remove the bolt, and disconnect the clamp and ground cable.
REMOVE IGNITION COIL ASSEMBLY
Disconnect the 8 ignition coil connectors.
Remove the 8 bolts and 8 ignition coil assemblies.
Note
Do not damage the ignition coil assemblies when removing them.
REMOVE CYLINDER HEAD COVER SUB-ASSEMBLY LH (for Bank 1)
Remove the fuel pump spacer gasket.
Remove the 16 bolts, 3 seal washers, cylinder head cover sub-assembly LH and cylinder head cover gasket LH.
Tech Tips
Make sure that the removed parts are returned to the original places they were removed from.
Remove the 2 oil hole gaskets and 2 O-rings from the camshaft bearing caps.
REMOVE CYLINDER HEAD COVER SUB-ASSEMBLY (for Bank 2)
Remove the fuel pump spacer gasket.
Remove the 16 bolts, 3 seal washers, cylinder head cover sub-assembly and cylinder head cover gasket.
Tech Tips
Make sure that the removed parts are returned to the original places they were removed from.
Remove the 2 oil hole gaskets and 2 O-rings from the camshaft bearing caps.
REMOVE OIL REFLECTOR PLATE LH (for Bank 1)
Remove the 2 bolts and oil reflector plate LH from the cylinder head assembly LH.
REMOVE OIL REFLECTOR PLATE RH (for Bank 2)
Remove the 2 bolts and oil reflector plate RH from the cylinder head assembly.
INSPECT NO. 1 CYLINDER TO TDC/COMPRESSION
Rotate the crankshaft clockwise to set the No. 1 cylinder to TDC compression by aligning the crankshaft pulley timing mark (notch) with the timing chain cover 0° position.
Check that each timing mark is positioned as shown in the illustration.
Tech Tips
If the timing marks are not positioned as shown in the illustration, rotate the crankshaft 360° to align the timing marks.
INSPECT VALVE CLEARANCE
Using a feeler gauge, measure the clearance between the indicated valve rocker arms and camshafts.
| Standard Valve Clearance (Cold) | ||||||
|---|---|---|---|---|---|---|
|
Tech Tips
On this engine, valve clearance is measured between the valve rocker arms and the camshaft lobes. The shims used to adjust the valve clearance are located on the top of the valve stems.
The valve clearance shown in the Standard Valve Clearance table is the clearance as measured between the cam lobe and valve rocker arm.
Record any out-of-specification valve clearance measurements. They will be used later to determine the required replacement valve adjusting shim.
Turn the crankshaft 1 revolution (360°) to set the No. 6 cylinder to TDC compression.
Using a feeler gauge, measure the clearance between the indicated valve rocker arms and camshafts.
| Standard Valve Clearance (Cold) | ||||||
|---|---|---|---|---|---|---|
|
Tech Tips
On this engine, valve clearance is measured between the valve rocker arms and the camshaft lobes. The shims used to adjust the valve clearance are located on the top of the valve stems.
The valve clearance shown in the Standard Valve Clearance table is the clearance as measured between the cam lobe and valve rocker arm.
Record any out-of-specification valve clearance measurements. They will be used later to determine the required replacement valve adjusting shim.
ADJUST VALVE CLEARANCE
Remove the timing chain cover sub-assembly Click here.
Remove the camshaft Click here.
Raise the valve rocker arm above the shim being replaced, and remove the valve adjusting shim.
Note
Be careful not to drop the adjusting shim into the cylinder head.
To prevent damage, do not attempt to adjust valve clearance by tightening or loosening the valve rocker arm pivots.
Tech Tips
Arrange the removed parts in the correct order.
Using a dial gauge, measure the thickness of the existing valve adjusting shim after removing it.
Tech Tips
Be careful not to measure at the valve adjusting shim center groove.
Determine the replacement valve adjusting shim thickness according to the formula or charts below.
Calculate the thickness of the replacement valve adjusting shim so that the valve clearance comes within the specified value.
| T2 | Thickness of replacement shim |
| T1 | Thickness of existing shim |
| A | Measured valve clearance |
| Valve clearance |
|---|
| Intake |
| T2 = T1 + (A - 0.15 mm (0.0059 in.)) x 1.8 |
| Exhaust |
| T2 = T1 + (A - 0.25 mm (0.0098 in.)) x 1.6 |
| This example is provided only as a calculation example, based on the clearance adjustment of an intake valve. If non-metric units are being used, substitute those measurements for the values shown below. Step 1 - Determining the amount of excess clearance
Step 2 - Using the existing valve adjusting shim to determine the required thickness of the replacement valve adjusting shim
Step 3 - Select the valve adjusting shim closest to the thickness of the ideal replacement shim
|
Tech Tips
Select a replacement shim with a thickness as close to the calculated value as possible.
Shims are available in 41 sizes in increments of 0.020 mm (0.0008 in.), from 2.000 mm (0.0787 in.) to 2.800 mm (0.1102 in.).
To select a replacement valve adjusting shim, refer to the following Valve Adjusting Shim Selection Chart and New Shim Thickness tables.
| Intake valve clearance (Cold) |
|---|
| 0.12 to 0.18 mm (0.00472 to 0.00709 in.) |
EXAMPLE:
If the existing shim (installed shim) is 2.300 mm (0.0906 in.), and the measured clearance is 0.39 mm (0.0154 in.), then a new 2.740 mm (0.1079 in.) No. 74 shim should be used as a replacement for the existing shim.
| Shim No. | Thickness | Shim No. | Thickness | Shim No. | Thickness |
|---|---|---|---|---|---|
| 00 | 2.000 (0.0787) | 28 | 2.280 (0.0898) | 56 | 2.560 (0.1008) |
| 02 | 2.020 (0.0795) | 30 | 2.300 (0.0906) | 58 | 2.580 (0.1016) |
| 04 | 2.040 (0.0803) | 32 | 2.320 (0.0913) | 60 | 2.600 (0.1024) |
| 06 | 2.060 (0.0811) | 34 | 2.340 (0.0921) | 62 | 2.620 (0.1031) |
| 08 | 2.080 (0.0819) | 36 | 2.360 (0.0929) | 64 | 2.640 (0.1039) |
| 10 | 2.100 (0.0827) | 38 | 2.380 (0.0937) | 66 | 2.660 (0.1047) |
| 12 | 2.120 (0.0835) | 40 | 2.400 (0.0945) | 68 | 2.680 (0.1055) |
| 14 | 2.140 (0.0843) | 42 | 2.420 (0.0953) | 70 | 2.700 (0.1063) |
| 16 | 2.160 (0.0850) | 44 | 2.440 (0.0961) | 72 | 2.720 (0.1071) |
| 18 | 2.180 (0.0858) | 46 | 2.460 (0.0969) | 74 | 2.740 (0.1079) |
| 20 | 2.200 (0.0866) | 48 | 2.480 (0.0976) | 76 | 2.760 (0.1087) |
| 22 | 2.220 (0.0874) | 50 | 2.500 (0.0984) | 78 | 2.780 (0.1094) |
| 24 | 2.240 (0.0882) | 52 | 2.520 (0.0992) | 80 | 2.800 (0.1102) |
| 26 | 2.260 (0.0890) | 54 | 2.540 (0.1000) |
| Exhaust valve clearance (Cold) |
|---|
| 0.22 to 0.28 mm (0.00866 to 0.0110 in.) |
EXAMPLE:
If the existing shim (installed shim) is 2.300 mm (0.0906 in.), and the measured clearance is 0.39 mm (0.0154 in.), then a new 2.520 mm (0.0992 in.) No. 52 shim should be used as a replacement for the existing shim.
| Shim No. | Thickness | Shim No. | Thickness | Shim No. | Thickness |
|---|---|---|---|---|---|
| 00 | 2.000 (0.0787) | 28 | 2.280 (0.0898) | 56 | 2.560 (0.1008) |
| 02 | 2.020 (0.0795) | 30 | 2.300 (0.0906) | 58 | 2.580 (0.1016) |
| 04 | 2.040 (0.0803) | 32 | 2.320 (0.0913) | 60 | 2.600 (0.1024) |
| 06 | 2.060 (0.0811) | 34 | 2.340 (0.0921) | 62 | 2.620 (0.1031) |
| 08 | 2.080 (0.0819) | 36 | 2.360 (0.0929) | 64 | 2.640 (0.1039) |
| 10 | 2.100 (0.0827) | 38 | 2.380 (0.0937) | 66 | 2.660 (0.1047) |
| 12 | 2.120 (0.0835) | 40 | 2.400 (0.0945) | 68 | 2.680 (0.1055) |
| 14 | 2.140 (0.0843) | 42 | 2.420 (0.0953) | 70 | 2.700 (0.1063) |
| 16 | 2.160 (0.0850) | 44 | 2.440 (0.0961) | 72 | 2.720 (0.1071) |
| 18 | 2.180 (0.0858) | 46 | 2.460 (0.0969) | 74 | 2.740 (0.1079) |
| 20 | 2.200 (0.0866) | 48 | 2.480 (0.0976) | 76 | 2.760 (0.1087) |
| 22 | 2.220 (0.0874) | 50 | 2.500 (0.0984) | 78 | 2.780 (0.1094) |
| 24 | 2.240 (0.0882) | 52 | 2.520 (0.0992) | 80 | 2.800 (0.1102) |
| 26 | 2.260 (0.0890) | 54 | 2.540 (0.1000) |
Install the camshaft Click here.
Install the chain sub-assembly Click here.
Install the chain sub-assembly (for Bank 2).
Install the No. 1 chain vibration damper (for Bank 2).
Install the chain tensioner slipper (for Bank 2).
Install the No. 1 chain tensioner assembly (for Bank 2).
Install the chain sub-assembly (for Bank 1).
Install the No. 1 chain vibration damper (for Bank 1).
Install the chain tensioner slipper (for Bank 1).
Install the No. 1 chain tensioner assembly (for Bank 1).
Tighten the camshaft timing gear assembly.
Inspect the valve clearance again.
Note
Be sure to inspect the valve clearance with the chain cub-assembly installed. When rotating the camshaft without the chain sub-assembly installed, contact between the valves and pistons may occur.
Tech Tips
If the valve clearance is not as specified, readjust the valve clearance.
INSTALL OIL REFLECTOR PLATE LH (for Bank 1)
Install the oil reflector plate LH with the 2 bolts.
INSTALL OIL REFLECTOR PLATE RH (for Bank 2)
Install the oil reflector plate RH with the 2 bolts.
INSTALL CYLINDER HEAD COVER SUB-ASSEMBLY LH (for Bank 1)
Install 2 new oil hole gaskets and 2 new O-rings to the camshaft bearing caps.
Install a new cylinder head cover gasket LH to the cylinder head cover sub-assembly LH.
Note
Remove any oil from the contact surface.
Apply seal packing as shown in the illustration.
| Seal packing |
|---|
| Toyota Genuine Seal Packing Black, Three Bond 1207B or equivalent |
Note
Remove any oil from the contact surface.
Install the cylinder head cover sub-assembly LH within 3 minutes and tighten the bolts within 15 minutes after applying seal packing.
Do not start the engine for at least 2 hours after installing the cylinder head cover sub-assembly LH.
Install the cylinder head cover sub-assembly LH with 3 new seal washers and the 16 bolts.
Install a new fuel pump spacer gasket.
INSTALL CYLINDER HEAD COVER SUB-ASSEMBLY (for Bank 2)
Install 2 new oil hole gaskets and 2 new O-rings to the camshaft bearing caps.
Install a new cylinder head cover gasket to the cylinder head cover sub-assembly.
Note
Remove any oil from the contact surface.
Apply seal packing as shown in the illustration.
| Seal packing |
|---|
| Toyota Genuine Seal Packing Black, Three Bond 1207B or equivalent |
Note
Remove any oil from the contact surface.
Install the cylinder head cover sub-assembly within 3 minutes and tighten the bolts within 15 minutes after applying seal packing.
Do not start the engine for at least 2 hours after installing the cylinder head cover sub-assembly.
Install the cylinder head cover sub-assembly with 3 new seal washers and the 16 bolts.
Install a new fuel pump spacer gasket.
INSTALL IGNITION COIL ASSEMBLY
Install the 8 ignition coil assemblies with the 8 bolts.
Note
Do not damage the ignition coil assemblies when installing them.
Connect the 8 ignition coil connectors.
CONNECT WIRE HARNESS
Connect the ground wire with the bolt and clamp.
Connect the ground cable with the bolt.
Connect the wire to the engine room No. 1 relay block. (for RHD)
Connect the clamp. (for RHD)
Connect the wire harness with the nut. (for RHD)
Install the No. 1 engine room relay block cover. (for RHD)
Connect the 7 clamps and connect the 5 connectors.
Install the 2 ground wires with the 2 bolts.
Connect the 3 clamps and 8 connectors.
Connect the 5 connectors and grommet to the engine room ECU box.
Engage the claw and connect the No. 4 connector holder to the engine room ECU box.
Connect the 3 connectors and connector clamp.
INSTALL FUEL PUMP ASSEMBLY (for Bank 1)
INSTALL FUEL PUMP ASSEMBLY (for Bank 2)