STARTER (for 1.6 kW Type) INSTALLATION


  1. INSTALL STARTER ASSEMBLY


    1. A01BEGIE01

      Install the starter with the 2 bolts.

      Torque:
      37 N*m  { 377 kgf*cm, 27 ft.*lbf }
    2. Connect the wire harness to terminal 30 and install the nut.

      Torque:
      9.8 N*m  { 100 kgf*cm, 87 in.*lbf }
    3. Connect the terminal 50 connector to the starter assembly.

    4. A01BFKRE01

      Install the ground cable and wire bracket with the 2 bolts.

      Torque:
      25 N*m  { 250 kgf*cm, 18 ft.*lbf }
  2. INSTALL TRANSMISSION CONTROL CABLE BRACKET NO.1 (for Automatic Transmission)


    1. A01BBN4E03

      Install the transmission control cable bracket to the automatic transmission assembly with the 2 bolts.

      Torque:
      14 N*m  { 143 kgf*cm, 11 ft.*lbf }
  3. INSTALL TRANSMISSION CONTROL CABLE ASSEMBLY (for Automatic Transmission)


    1. A01BGU8E04

      Install the transmission control cable assembly to the control shaft lever and transmission control bracket No.1 with the nut and a new clip.

      Torque:
      15 N*m  { 150 kgf*cm, 11 ft.*lbf }
  4. INSTALL ENGINE SIDE UNDER COVER LH (w/ Engine Side Under Cover LH)

    Torque:
    13 N*m  { 133 kgf*cm, 10 ft.*lbf }
  5. INSTALL ENGINE SIDE UNDER COVER RH (w/ Engine Side Under Cover RH)

    Torque:
    13 N*m  { 133 kgf*cm, 10 ft.*lbf }
  6. INSTALL ENGINE UNDER COVER NO.2 (w/ Engine Under Cover No.2)

    Torque:
    13 N*m  { 133 kgf*cm, 10 ft.*lbf }
  7. CONNECT NEGATIVE BATTERY CABLE

  8. PERFORM INITIALIZATION


    1. Some system need initialization when reconnecting the battery cable. Click here