OIL COOLER INSTALLATION

PROCEDURE


  1. INSTALL TRANSMISSION OIL COOLER


    1. Apply Toyota genuine CVT Fluid TC to the 2 new O-rings and install them on the transmission oil cooler.

    2. Install the transmission oil cooler onto the continuously variable transaxle with the 3 bolts.

      Torque:
      21 N*m  { 214 kgf*cm, 15 ft.*lbf }
  2. INSTALL WATER BY-PASS HOSE ASSEMBLY


    1. Install the 2 water by-pass hoses to the transmission oil cooler with the 2 clamps.

      Note

      Securely push the hoses over each pipe fitting on the transmission oil cooler until the hoses contact the rib on each pipe fitting.

  3. ADD ENGINE COOLANT

    Click here

  4. INSPECT FOR ENGINE COOLANT LEAK

    Click here

  5. ADJUST CVT FLUID

    Click here

  6. INSPECT FOR CVT FLUID LEAK

  7. INSTALL ENGINE UNDER COVER LH

    Click here