SHIFT LEVER INSTALLATION

PROCEDURE


  1. INSTALL SHIFT LEVER ASSEMBLY


    1. Engage the 3 clamps and install the wire harness to the shift lever assembly.

    2. Connect the 2 connectors to the shift lever assembly.

    3. Temporarily install the shift lever assembly with the 4 bolts.

    4. A01VGXME01

      Fully tighten the 4 bolts in the order shown in the illustration.

      Torque:
      12 N*m  { 122 kgf*cm, 9 ft.*lbf }
  2. CONNECT TRANSMISSION CONTROL CABLE ASSEMBLY


    1. A01VDZNE06
      Text in Illustration
      *1 Nut
      *2 Lock
      *a Rotate Approximately 180°
      *b Push In

      Rotate the nut of the transmission control cable approximately 180° in the direction shown in the illustration, and while holding the nut, push in the lock.

      Note

      Rotating the nut too much will damage the internal spring, and the transmission control cable assembly will not be reusable. Do not turn the nut too far.

    2. A01VGE4E02
      Text in Illustration
      *1 Lock
      *2 Shift Lever Plate
      *a Tab

      Install the transmission control cable assembly to the shift lever plate.

      Note


      • Install the cable outer with the tab facing upwards.

      • After installation, check that the cable outer lock extends past section A as shown in the diagram.

    3. Confirm that the shift lever is in N, and then connect the cable end to the shift lever assembly.

      Note


      • Securely install the cable end to the shift lever assembly.

      • Install the cable end so that its adjustment lock section is on the driver side.

  3. ADJUST SHIFT LEVER POSITION

    Click here

  4. INSTALL REAR CONSOLE BOX

    Click here

  5. INSTALL SHIFT LEVER KNOB SUB-ASSEMBLY


    1. A01VGW9

      Turn the shift lever knob sub-assembly clockwise and install the shift lever knob sub-assembly.

  6. INSPECT SHIFT LEVER POSITION

    Click here