TOE CONTROL LINK INSPECTION

Click here
Click here Click here

CAUTION / NOTICE / HINT

Tip:
  • Use the same procedure for the RH and LH side.

  • The following procedure is for the LH side.

Click here

PROCEDURE


  1. Click here

    INSPECT TOE CONTROL LINK SUB-ASSEMBLY LH


    1. B004W38

      Inspect the turning torque of the ball joint.


      1. Install the nut to the toe control link sub-assembly LH stud.

      2. Using a torque wrench, turn the stud continuously at a rate of 2 to 4 seconds per turn and take the torque reading on the 5th turn.

        Turning torque
        0.9 to 3.5 N*m (10 to 35 kgf*cm, 8 to 30 in.*lbf)

        If the turning torque is not within the specified range, replace the toe control link sub-assembly LH with a new one.

    2. Inspect the dust cover.


      1. Check that the dust cover is not cracked and that there is no grease on it.

        If the dust cover is cracked or there is grease on it, toe control link sub-assembly LH with a new one.