HV BATTERY STACK INSPECTION

PROCEDURE


  1. INSPECT HV SUPPLY STACK SUB-ASSEMBLY

    CAUTION:

    Be sure to wear insulated gloves and protective goggles.


    1. Remove the HV supply stack sub-assembly.

      Click here

    2. Inspect the HV supply stack sub-assembly.


      1. Check that no electrolyte is leaking from the No. 1 HV supply stack sub-assembly or No. 2 HV supply stack sub-assembly.

        B000SRCC01
        *1 No. 1 HV Supply Stack Sub-assembly *2 No. 2 HV Supply Stack Sub-assembly
        *a Check Part - -
        OK
        There is no electrolyte leaking from the HV supply stack sub-assembly.

        Tech Tips

        If the result is not as specified, replace the No. 1 HV supply stack sub-assembly or No. 2 HV supply stack sub-assembly.

    3. Install the HV supply stack sub-assembly.

      Click here