ENGINE OIL COOLER INSTALLATION

PROCEDURE


  1. INSTALL OIL COOLER ASSEMBLY


    1. Install the No. 1 cylinder block insulator and 2 new O-rings.

    2. Install the oil cooler assembly with the 2 bolts and 2 nuts.

      Torque:
      21 N*m  { 214 kgf*cm, 15 ft.*lbf }
    3. Connect the No. 4 water by-pass hose and No. 5 water by-pass hose to the oil cooler assembly, and slide the 2 clips to secure them.

    4. Install the hose clamp with the nut.

      Torque:
      10 N*m  { 102 kgf*cm, 7 ft.*lbf }
  2. INSTALL EXHAUST MANIFOLD ASSEMBLY LH

    Click here

  3. ADD ENGINE OIL

    Click here

  4. ADD ENGINE COOLANT

    Click here

  5. CHECK ENGINE OIL LEVEL

    Click here

  6. INSPECT FOR ENGINE OIL LEAK

    Click here

  7. INSPECT FOR COOLANT LEAK

    Click here