ROOF DRIP SIDE FINISH MOULDING INSTALLATION

CAUTION / NOTICE / HINT

Tech Tips


  • Use the same procedure for the RH side and LH side.

  • The following procedure is for the LH side.

PROCEDURE


  1. INSTALL ROOF DRIP SIDE FINISH MOULDING CLIP

    Note

    When installing new roof drip side finish moulding clips, remove the double-sided tape remaining where the roof drip side finish moulding clips will be installed on the vehicle body and clean the vehicle body with non-residue solvent.


    1. A01Q9YX

      Apply a 2 to 3 mm (0.0787 to 0.118 in.) bead of adhesive (3M DP-105 or equivalent) to 11 new roof drip side finish moulding clips.

      Tech Tips

      Adhesive strength (tensile strength): 13.7 MPa (140.0 kgf/cm2, 1987 psi) or more (when the temperature is 23°C (73°F).)

    2. Install the roof drip side finish moulding clips to the positions on the roof panel shown in the illustration. Determine the locations and firmly press and install the 2 roof drip side finish moulding clips after lightly applying adhesive.

      A01QCOJN02
      Standard Measure
      Area Measurement Area Measurement
      A 3.5 to 4.5 mm (0.138 to 0.177 in.) B 3.5 to 4.5 mm (0.138 to 0.177 in.)
      C 1.4 to 2.4 mm (0.055 to 0.094 in.) D 3.5 to 4.5 mm (0.138 to 0.177 in.)
      E 3.5 to 4.5 mm (0.138 to 0.177 in.) F 0.8 to 1.8 mm (0.031 to 0.071 in.)
    3. Install the center roof drip side finish moulding when 20 minutes or more have elapsed after pressing and installing the 2 roof drip side finish moulding clips.

      Tech Tips


      • Initial hardening time: 20 minutes

      • Complete hardening time: 48 hours

  2. INSTALL CENTER ROOF DRIP SIDE FINISH MOULDING


    1. Engage the roof drip side finish moulding clips to install the center roof drip side finish moulding.