BATTERY CURRENT SENSOR INSTALLATION

PROCEDURE

  1. INSTALL GENERATOR CONTROL ECU ASSEMBLY

    1. A288520C01

      *1

      Engine Wire

      *2

      Generator Control ECU Assembly

      *3

      Negative (-) Battery Terminal

      Install the negative (-) battery terminal to the battery and tighten the nut.

      5.4 N*m

      55 kgf*cm

      48 in.*lbf

    2. Install the generator control ECU assembly and nut to the negative (-) battery terminal.

      7.6 N*m

      77 kgf*cm

      67 in.*lbf

    3. Connect the connector to the generator control ECU assembly.

    4. Connect the engine wire to the generator control ECU assembly and install the nut.

      7.6 N*m

      77 kgf*cm

      67 in.*lbf