ROOF DRIP SIDE FINISH MOULDING INSTALLATION

Tech Tips


  • Use the same procedure for the RH and LH sides.

  • The procedure listed below is for the LH side.


  1. INSTALL NO. 1 ROOF DRIP SIDE FINISH MOULDING CLIP

    Note


    • It is only necessary to perform this procedure when replacing a No. 1 roof drip side finish moulding clip with a new one.

    • If installing new No. 1 roof drip side finish moulding clips, remove the adhesive remaining where the No. 1 roof drip side finish moulding clips will be installed on the vehicle body and clean the vehicle body with a non-residue solvent.

    Tech Tips

    When installing the No. 1 roof drip side finish moulding clip, heat the vehicle body and No. 1 roof drip side finish moulding clip using a heat light.

    Standard
    Item Temperature
    Vehicle Body 40 to 60°C (104 to 140°F)
    No. 1 Roof Drip Side Finish Moulding Clip 20 to 30°C (68 to 86°F)

    Note

    Do not heat the vehicle body or No. 1 roof drip side finish moulding clip excessively.


    1. A01DWT4E02
      Text in Illustration
      *1 Adhesive
      *a 2 to 3 mm Bead of Adhesive

      Apply a 2.0 to 3.0 mm (0.0787 to 0.118 in.) bead of adhesive (3M DP-105 or equivalent) to new No. 1 roof drip side finish moulding clips.

      Tech Tips

      Adhesive strength (tensile strength): 13.7 MPa (140.0 kgf/cm2, 1991 psi) or more (when the temperature is 23°C (73°F))

    2. Apply primer to the body where the No. 1 roof drip side finish moulding clip will be installed.

      Note

      Do not let the primer dry.

    3. A01DXKBE01
      Text in Illustration
      *A for Single Cab
      *B for Double Cab
      *C for Extra Cab

      While using the position shown in the illustration as a reference, place the No. 1 roof drip side finish moulding clip onto the roof panel. Then position and install the No. 1 roof drip side finish moulding clip after lightly pressing it so that the adhesive adheres to the primer.

      Standard
      Area Measurement (Reference Value)
      A 40.7 mm (1.60 in.)
      B 47.6 mm (1.87 in.)
      C 40.7 mm (1.60 in.)
      D 39.2 mm (1.54 in.)
      E 40.7 mm (1.60 in.)
      F 42.9 mm (1.69 in.)

      Note

      Install the roof drip side finish moulding when 40 minutes or more have elapsed after pressing and installing the No. 1 roof drip side finish moulding clips.

      Tech Tips


      • Initial hardening time: 40 minutes

      • Complete hardening time: 48 hours

  2. INSTALL ROOF DRIP SIDE FINISH MOULDING LH


    1. Attach the 2 clips to install the roof drip side finish moulding.