MANUAL TRANSMISSION ASSEMBLY (for 2TR-FE) INSTALLATION


  1. INSTALL WIRE HARNESS CLAMP BRACKET


    1. B007T4X

      Install the wire harness clamp bracket.

      Torque:
      37 N*m  { 377 kgf*cm, 27 ft.*lbf }
  2. INSTALL TRANSMISSION CONTROL CABLE BRACKET NO.1


    1. Install the transmission control cable bracket No.1 with the 2 bolts.

      Torque:
      28 N*m  { 286 kgf*cm, 21 ft.*lbf }
  3. INSTALL REAR ENGINE MOUNTING INSULATOR ASSEMBLY


    1. B007V53

      Install the rear engine mounting insulator assembly with the 4 bolts.

      Torque:
      29 N*m  { 296 kgf*cm, 21 ft.*lbf }
  4. INSTALL MANUAL TRANSMISSION UNIT ASSEMBLY


    1. B007RMKE01

      Install the transmission unit assembly with the 8 bolts.

      Torque:
      Bolt A
      72 N*m  { 729 kgf*cm, 53 ft.*lbf }
      Bolt B
      37 N*m  { 377 kgf*cm, 27 ft.*lbf }
    2. B007SFJ

      Install the transmission unit assembly to the frame with the bolt, nut, and 2 washers.

      Torque:
      98 N*m  { 999 kgf*cm, 72 ft.*lbf }

      Note


      • Insert the bolt from the left side of the vehicle.

      • Tighten the nut while holding the bolt.

  5. INSTALL STARTER ASSEMBLY (for 2.0 kW Type)


    1. Install the starter assembly with the 2 bolts.

      Torque:
      37 N*m  { 377 kgf*cm, 27 ft.*lbf }
    2. Connect the starter wire harness with the nut.

      Torque:
      9.8 N*m  { 100 kgf*cm, 87 in.*lbf }
    3. Connect the starter connector.

    4. Close the terminal cap.

    5. Connect the ground cable and wiring harness clamp bracket with the 2 bolts.

      Torque:
      25 N*m  { 251 kgf*cm, 18 ft.*lbf }
  6. INSTALL STARTER ASSEMBLY (for 1.7 kW Type)


    1. Install the starter assembly with the 2 bolts.

      Torque:
      37 N*m  { 377 kgf*cm, 27 ft.*lbf }
    2. Connect the starter wire and install the nut.

      Torque:
      9.8 N*m  { 100 kgf*cm, 87 in.*lbf }
    3. Connect the starter connector.

    4. Close the terminal cap.

    5. Connect the ground cable and wiring harness clamp bracket with the 2 bolts.

      Torque:
      25 N*m  { 251 kgf*cm, 18 ft.*lbf }
  7. INSTALL STARTER ASSEMBLY (for 1.6 kW Type)


    1. B007VFYE01

      Install the starter with the 2 bolts.

      Torque:
      37 N*m  { 377 kgf*cm, 27 ft.*lbf }
    2. Connect the wire harness to terminal 30 and install the nut.

      Torque:
      9.8 N*m  { 100 kgf*cm, 87 in.*lbf }
    3. Connect the terminal 50 connector to the starter assembly.

    4. B007UWAE01

      Install the ground cable and wire bracket with the 2 bolts.

      Torque:
      25 N*m  { 250 kgf*cm, 18 ft.*lbf }
  8. INSTALL CLUTCH RELEASE CYLINDER ASSEMBLY


    1. B007VM7

      Install the clutch release cylinder with the 2 bolts.

      Torque:
      12 N*m  { 120 kgf*cm, 9 ft.*lbf }
  9. INSTALL WIRE HARNESS


    1. B007ONV

      Connect the 2 connectors and clamps.

  10. INSTALL TRANSMISSION CONTROL CABLE ASSEMBLY


    1. B007T5UE01

      Install 2 new clips to the transmission control cable bracket No.1.

    2. Install the transmission control cable assembly to the transmission control cable bracket No.1.

      Note


      • Be sure that A claws of the clips are firmly engaged into the bracket grooves.

      • Be sure the cable is set in the clip with both B claws erected to prevent slippage of the cable in the opposite direction.

    3. B007VCTE01

      Align the matchmarks on the control cable assembly and the outer lever.

    4. Install the transmission control cable assembly to the outer levers with the 2 nuts.

      Torque:
      37 N*m  { 377 kgf*cm, 27 ft.*lbf }
  11. INSTALL PROPELLER SHAFT ASSEMBLY (for Long Wheelbase)


    1. B007UO6E01

      Remove the SST from the extension housing.

    2. Install the propeller shaft assembly in the extension housing.

    3. Align the matchmarks on the propeller shaft flange and differential flange.

    4. B007W0TE01

      Install the propeller shaft assembly with the 4 nuts, 4 bolts and 4 washers.

      Torque:
      74 N*m  { 755 kgf*cm, 54 ft.*lbf }
  12. INSTALL PROPELLER WITH CENTER BEARING SHAFT ASSEMBLY (for Super Long Wheelbase)


    1. B007UO6E01

      Remove the SST from the extension housing.

    2. Install the propeller with center bearing shaft assembly in the extension housing.

    3. B007PGH

      Install the center support bearing assembly No.1, and temporarily tighten the 2 bolts.

    4. B007W0TE01

      Align the matchmarks on the propeller shaft flange and differential flange.

    5. Install the propeller shaft assembly with the 4 nuts, 4 bolts and 4 washers.

      Torque:
      74 N*m  { 755 kgf*cm, 54 ft.*lbf }
    6. B007P1EE01

      Check that the center line of the bracket is at right angles to the shaft axial direction.

    7. B007T3NE01

      Adjust the center support bearing assembly No.1.

      Tech Tips


      • With the vehicle unladen, adjust the center support bearing No.1 to maintain the angles, as shown.

      • In the same conditions, check the center line in the axial direction. Adjust the bearing if necessary.

      • The center bearing center line and center bearing housing center line must be adjusted to within -1.0 to 1.0 mm (-0.0394 to 0.0394 in.) of each other in the vehicle's longitudinal direction with the vehicle unladen.

    8. Tighten the 2 bolts.

      Torque:
      36 N*m  { 369 kgf*cm, 27 ft.*lbf }
  13. INSTALL EXHAUST PIPE ASSEMBLY FRONT (for Long Wheelbase)


    1. w/ Secondary air injection system:


      1. Install the fuel ratio sensor. Click here

        Torque:
        44 N*m  { 449 kgf*cm, 32 ft.*lbf }
    2. For unleaded gasoline engine:


      1. Install the oxygen sensor. Click here

        Torque:
        44 N*m  { 449 kgf*cm, 32 ft.*lbf }
    3. Inspect the compression spring.


      1. B007PNQ

        Using vernier calipers, measure the free length of the compression springs.

        Minimum length
        40.5mm(1.594 in.)

        Tech Tips

        If the free length is less than the minimum, replace the compression spring.

    4. B007R45E03

      Install the gasket.


      1. Fully insert a new gasket to the exhaust manifold by hand.

      2. Using a wooden block, uniformly strike the gasket so that the gasket and exhaust manifold are properly fit.

        Note


        • Be careful with the installation direction of the gasket.

        • Do not reuse the gasket.

        • Do not damage the gasket.

        • To ensure a proper seal, do not use the exhaust pipe assembly front to force the gasket onto the exhaust manifold.

    5. Install a new gasket to the exhaust pipe assembly front.

    6. Connect the exhaust pipe assembly front to the exhaust pipe support.

    7. Install the exhaust pipe assembly front with the 4 bolts, 2 nuts, and 2 compression springs.

      Torque:
      Exhaust manifold side
      43 N*m  { 438 kgf*cm, 32 ft.*lbf }
      Torque:
      Exhaust pipe assembly tail side
      48 N*m  { 489 kgf*cm, 35 ft.*lbf }

      Note

      After installation, check that the clearance is almost the same at any point between the flanges of the exhaust manifold and exhaust pipe assembly front.

    8. For unleaded gasoline engine:


      1. Connect the sensor connector(s).

  14. INSTALL EXHAUST PIPE ASSEMBLY FRONT (for Super Long Wheelbase)


    1. w/ Secondary air injection system:


      1. Install the air fuel ratio sensor. Click here

        Torque:
        44 N*m  { 449 kgf*cm, 32 ft.*lbf }
    2. For Unleaded gasoline engine:


      1. Install the oxygen sensor. Click here

        Torque:
        44 N*m  { 449 kgf*cm, 32 ft.*lbf }
    3. Inspect the compression spring.


      1. B007PNQ

        Using vernier calipers, measure the free length of the compression springs.

        Minimum length
        40.5 mm (1.594 in.)

        Tech Tips

        If the free length is less than the minimum, replace the compression spring.

    4. B007R45E03

      Install the gasket.


      1. Fully insert a new gasket to the exhaust manifold by hand.

      2. Using a wooden block, uniformly strike the gasket so that the gasket and exhaust manifold are properly fit.

        Note


        • Be careful with the installation direction of the gasket.

        • Do not reuse the gasket.

        • Do not damage the gasket.

        • To ensure a proper seal, do not use the exhaust pipe assembly front to force the gasket onto the exhaust manifold.

      3. Install a new gasket to the exhaust pipe assembly front.

      4. Connect the exhaust pipe assembly front to the exhaust pipe support.

      5. Install the exhaust pipe assembly front with the 4 bolts, 2 nuts, and 2 compression springs.

        Torque:
        Exhaust manifold side
        43 N*m  { 438 kgf*cm, 32 ft.*lbf }
        Exhaust pipe assembly center side
        48 N*m  { 489 kgf*cm, 35 ft.*lbf }

        Note

        After installation, check that the clearance is almost the same at any point between the flanges of the exhaust manifold and exhaust pipe assembly front.

    5. For Unleaded gasoline engine:


      1. Connect the sensor connector(s).

  15. ADD MANUAL TRANSMISSION OIL


    1. B007P4BE01

      Park the vehicle in a level place.

    2. Remove the transmission filler plug and gasket.

    3. Check that the oil surface is within 5 mm (0.20 in.) below the lowest point of the transmission filler plug opening.

      Oil grade
      API GL-4
      Viscosity
      SAE 75W-90
      Capacity
      2.6 liters (2.7 US qts, 2.3 Imp.qts)

      Note


      • Problems may occur when the oil level is too high or too low.

      • After replacing the oil, drive the vehicle and check the oil level again.

    4. Check for oil leakage if the oil level is low.

    5. Install the transmission filler plug and a new gasket.

      Torque:
      37 N*m  { 377 kgf*cm, 27 ft.*lbf }
  16. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

  17. CHECK FOR EXHAUST GAS LEAKS

  18. PERFORM INITIALIZATION

    Some systems need initialization after reconnecting the cable to the negative battery terminal. Click here